Quali-Quantitative Analysis of Brazilian Environmental Licensing of Hydropower Plants
- 1 Federal University of Rio de Janeiro, Rio de Janeiro, Brazi
- 2 Federal University of Rio de Janeiro, Rio de Janeiro, Brazi
- 3 Federal University of Rio de Janeiro, Rio de Janeiro, Brazi
- 4 Federal University of Rio de Janeiro, Rio de Janeiro, Brazi
- 5 Federal University of Rio de Janeiro, Rio de Janeiro, Brazi
- 6 Federal University of Rio de Janeiro, Rio de Janeiro, Brazi
- 7 National School of Statistical Sciences, Rio de Janeiro, Brazi
- 8 State University of Rio de Janeiro, Rio de Janeiro, Brazi
Abstract
The use of the extraordinary hydroelectric potential of the Amazon Basin originated an increase in the offer of renewable energy in Brazil, which, in its turn, leads to conflicts and a lack of consensus among different players owing to the potential negative impacts related to the construction and operation of large hydroelectric power plants in relatively well preserved areas. In this context, environmental licensing is one of the national environmental policy’s main instruments for making decisions regarding the use of the hydroelectric potential, especially the rivers of the Amazon Basin. Nevertheless, this significant instrument has its limitations and requires adjustments in order to better aid the decision making process regarding the use of water resources and land with the goal of increasing the offer of electric energy.
- Eletrobras (2015) Sistema Brasileiro de Informa??es do Potencial Hidrelétrico (SIPOT).
- Bechberger, M. and Reiche, D. (2004) Renewable Energy Policy in Germany: Pioneering and Exemplary Regulations. Energy for Sustainable Development, 8, 47-57.
- Georgopoulou, E., Sarafidis, Y. and Diakoulaki, D. (1998) Design and Implementation of a Group DSS for Sustaining Renewable Energies Exploitation. European Journal of Operational Research, 109, 483-500. http://dx.doi.org/10.1016/S0377-2217(98)00072-1
- Resch, G., Held, A., Faber, T., Panzer, C., Toro, F. and Haas, R. (2008) Potentials and Prospects for Renewable Energies at Global Scale. Energy Policy, 36, 4048-4056. http://dx.doi.org/10.1016/j.enpol.2008.06.029
- Pereira, M.G., Freitas, M.A.V. and da Silva, N.F. (2011) The Challenge of Energy Poverty: Brazilian Case Study. Energy Policy, 39, 167-175. http://dx.doi.org/10.1016/j.enpol.2010.09.025
- Brasil (2007) Ministério de Minas e Energia. Plano Nacional de Energia 2030/Ministério de Minas e Energia; colabora??o Empresa de Pesquisa Energética. Brasília, 324 p.
- World Commission on Dams (2000) Dams and Development: A New Framework for Decision-Making. The Report of the World Commission on Dams, Earthscan Publications Ltd., London and Sterling.
- Heinma, K. and P?der, T. (2010) Effectiveness of Environmental Impact Assessment System in Estonia. Environmental Impact Assessment Review, 30, 272-277. http://dx.doi.org/10.1016/j.eiar.2009.10.001
- Che, X.Z., English, A., Lu, J. and Chen, Y.Q.D. (2011) Improving the Effectiveness of Planning EIA (PEIA) in China: Integrating Planning and Assessment during the Preparation of Shenzhen’s Master Urban Plan. Environmental Impact Assessment Review, 31, 561-571. http://dx.doi.org/10.1016/j.eiar.2010.12.003
- Nykvist, B. and Nilsson, M. (2009) Are Impact Assessment Procedures Actually Promoting Sustainable Development? Institutional Perspectives on Barriers and Opportunities Found in the Swedish Committee System. Environmental Impact Assessment Review, 29, 15-24. http://dx.doi.org/10.1016/j.eiar.2008.04.002
- P?l?nen, I., Hokkanen, P. and Jalava, K. (2011) The Effectiveness of the Finnish EIA System—What Works, What Doesn’t, and What Could Be Improved? Environmental Impact Assessment Review, 31, 120-128. http://dx.doi.org/10.1016/j.eiar.2010.06.003
- Samarakoon, M. and Rowan, J.S. (2008) A Critical Review of Environmental Impact Statements in Sri Lanka with Particular Reference to Ecological Impact Assessment. Environmental Management, 41, 441-460.