Productivity Monitoring of Land Pipelines Welding via Control Chart Using the Monte Carlo Simulation
- 1 Department of Graduation in Civil Engineering, Federal Fluminense University, Niterói, Brazil
- 2 Mechanical Engineering Department, Federal Fluminense University, Niterói, Brazil
Abstract
This article evaluates the efficacy of a tool developed in the Monte Carlo simulation and referred to as control chart. This tool is used in order to detect changes in productivity resulting from the occurrence of a given event during the welding of land pipelines with self shielded flux cored wire (FCAW). The elaboration of this control chart is based on the data from the Cumulative Probability Density Function (CDF) curve, and generated in the Monte Carlo simulation using version 6 of the Palisade Corporation’s @Risk software for Excel, in a sample with productivity data from 29 welded joints, gathered through direct observation which considers the productive and unproductive times. In order to evaluate the control chart efficacy, the performance of welding productivity with a FCAW process with low alloy steels has been assessed during 29 days, summing up to 842 welded joints registered on “Relatórios Diários de Obras” (Construction Works Daily Reports). The results show that the model developed for the control chart elaboration is effective in monitoring the productivity of the observed welding procedure.
- Miller, C. and Crawford, M.H. (2002) Welding-Related Expenditures, Investments, and Productivity Measurement in U.S. Manufacturing, Construction, and Mining Industries. Technical Report, American Welding Society, Miami.
- Ritzman, L.P. and Krajewski, L.J. (2003) Foundations of Operations Management. 2nd Edition, Prentice Hall, Upper Saddle River.
- Slack, N., Chambers, S. and Johnston, R. (2002) Operations Management. 2nd Edition, Atlas, Sao Paulo.
- Gaither, N. and Frazier, G. (2002) Production and Operations Management. Thomson Learning, Sao Paulo.
- Diekmann, J.E. and Heinz, J. (2001) Determinants of Jobsite Productivity. Construction Industry Institute, Austin.
- de Souza, U.E.L. (2006) How to Increase Labor Efficiency: Productivity Management Manual in Construction. 1st Edition, Pini, Sao Paulo.
- Adrian, J.J. (2004) Construction Productivity: Measurement and Improvement. Stipes Publishing, Champaign.
- Schwartzkoft, W. (2004) Calculating Lost Labor Productivity in Construction Claims. Aspen, Austin.
- Construction Industry Institute (2010) Guide to Activity Analysis. University of Texas, Austin.
- Gioia, A.L.S., Silva Júnior, I.F. (2007) Assessment of Methodology for Productivity Measurement in Pipe Instalation Activity in Industrial Works. Graduation, Monograph, University Federal Fluminense, Niterói.
- Martins, J.L.F. (2011) Application of Simulation with Monte Carlo and Latin Hypercube Methods to Estimate Productivity in the Welding Process of SMAW. PhD Thesis, University Federal Fluminense, Niterói.
- Martins, J.L.F., Ferreira, M. and Saraiva, J.M.F. (2011) Productivity Estimation in Welding by Monte Carlo Method. Soldagem e Inspecao, 16, 204-212.
- Constancio, D.S., Ferreira, M. and Freire, I.J. (2009) Welding Productivity’s Estimate of Industrial Piping, Being Used Monte Carlo’s Method. Proceedings of the XXXV CONSOLDA—Congresso Nacional de Soldagem, Piracicaba, 26-29 Outubro 2009, 26-29.
- Morano, C.A.R. (2003) Application of Risk Analysis Techniques in Construction Projects. Master’s Dissertation, University Federal Fluminense, Niterói.
- Grey, S. (1995) Practical Risk Assessment for Project Management. John Wiley & Sons, Chichester.
- Vose, D. (2000) Risk Analysis: A Quantitative Guide. 2nd Edition, John Wiley & Sons, Chichester.