Causes of Delay in Construction of Motorable Bridges under “Design and Build Model” of Bridge Project, Department of Roads, Nepal
- 1 Lincoln University College, Kelantan, Malaysia
- 2 Lincoln University College, Kelantan, Malaysia
- 3 Pokhara University, Pokhara, Nepal
Abstract
This paper aims at detecting the causes of delay in the “design and build model” of motorable bridge construction under the Bridge Project, Department of Roads, Nepal. The research is based on an intensive literature review, primary data, secondary data, and interviews. The survey which was carried out with the help of questionnaires was used to assess the perceptions of the respondents involved in the construction of the “design and build model” of the bridge project. The questionnaire was divided into three parts and the main part focused on the causes of delay in “design and build model” in the implementation of such projects. A total of 56 different causes for delay of bridge construction were identified through the literature review and a pilot survey of three groups of respondents who were involved in the construction of such bridges (see literature review of this paper). The eight most important causes, among 56, identified by the study are: 1) Lack of stakeholder analysis 2) Poor portfolio management 3) Lack of inadequate pre-execution planning and improper time management 4) Lack of site management 5) Inadequate budget allocation and delay in payment 6) Lack of provision of reward and penalty, 7) Lack of detail survey, improper soil exploration and preparing report without depth study and 8) contractor’s excessive workload. The cost, quality, and schedule of bridge construction projects can be maintained once the problem of unnecessary delay is resolved and the competency of the construction industry in Nepal will improve.
- Abdullah, M. R., Rahman, I. A., & Azis, A. A. A. (2010). Causes of Delay in MARA Management Procurement Construction Projects. Journal of Surveying, Construction and Property, 1, 123-138. https://doi.org/10.22452/jscp.vol1no1.6
- Ahmad, Z. B., Anigbogu, N. A., & Molwus, J. J. (2018). Peculiarities of Road Projects’ Cost Overruns. International Journal of Scientific & Engineering Research, 9, 121-124.
- Al-Hazim, N., Salem, Z. A., & Ahmad, H. (2017). Delay and Cost Overrun in Infrastructure Projects in Jordan. Procedia Engineering, 182, 18-24. https://doi.org/10.1016/j.proeng.2017.03.105
- Alzara, M., Kashiwagi, J., Kashiwagi, D., & Al-tassan, A. (2016). Using PIPS to Minimize Causes of Delay in Saudi Arabian Construction Projects: University Case Study. Procedia Engineering, 145, 932-939. https://doi.org/10.1016/j.proeng.2016.04.121
- Bista, S. B., & Dahal, R. K. (2018). Assessment of Low Bidding in Bridge Construction with Special Reference to Nepal. International Journal of Research Granthaalayah, 6, 71-80.
- Gidado, K., & Niazai, G. (2012). Causes of Project Delay in the Construction Industry in Afghanistan. In EPPM 2012 Conference Papers (pp. 63-74). Brighton, UK: University of Brighton. https://doi.org/10.32738/CEPPM.201209.0007
- Gluszak, M., & Lesniak, A. (2015). Construction Delays in Client Opinion—Multivariate Statistical Analysis. Procedia Engineering, 123, 182-189. https://doi.org/10.1016/j.proeng.2015.10.075
- Hasan, R., Suliman, S., & Al Malki, Y. (2014). An Investigation into the Delays in Road Projects in Bahrain. International Journal of Engineering Science, 2, 38-47.
- Haseeb, M., Lu, X., Bibi, A, Dyian, M. U., & Rabbani, W. (2011). Problems of Projects and Effects of Delay in the Construction Industry of Pakistan. Australian Journal of Business and Management Research, 1, 41-50.
- Honrao, Y., & Desai, D. B. (2015). Study of Delay in Execution of Infrastructure Projects. International Journal of Scientific and Research Publications, 5, 1-8.
- Hossen, M. M., Kang, S., & Kim, J. (2015). Construction Schedule Delay Risk Assessment by Using Combined AHP-RII Methodology for an International NPP Project. Nuclear Engineering and Technology, 47, 362-379. https://doi.org/10.1016/j.net.2014.12.019
- Hytiris, N., Stott, R., & McInnes, K. (2014). The Importance of Site Investigation in the Construction Industry: A Lesson to Be Taught to Every Graduate Civil and Structural Engineer. World Transactions on Engineering and Technology Education, 12, 414-419.