Critical Success Factors for Private-Public Partnerships in Irrigation Development: Case Study of Galana Kulalu Irrigation Project
- 1 Department of Civil, Construction and Environmental Engineering, Jomo Kenyatta University of Agriculture and Technology, Nairobi, Kenya
- 2 Department of Civil, Construction and Environmental Engineering, Jomo Kenyatta University of Agriculture and Technology, Nairobi, Kenya
- 3 Department of Civil, Construction and Environmental Engineering, Jomo Kenyatta University of Agriculture and Technology, Nairobi, Kenya
Abstract
The success of Public-Private Partnership (PPP) irrigation projects hinges on realistic project scoping, thorough feasibility analysis, and the early involvement of qualified technical expertise. The Galana Kulalu Irrigation Project, initially conceived as a 1,000,000-acre scheme, has faced delays, cost overruns, and reduced output, raising concerns about inflated targets at the formulation stage and the adequacy of preparatory studies. This study, grounded in the Theory of Constraints (TOC) and Principal-Agent Theory, examines whether critical success factors (CSFs) were sufficiently addressed from conception to implementation. Using survey data from 92 purposively sampled stakeholders and triangulated with official audits, the study found that the original scope far exceeded available water resources and operational capacity, with no evidence of a comprehensive, independent feasibility study prior to commitment. Limited participation of experienced irrigation and agricultural engineers in the conceptualization stage contributed to unrealistic timelines, underestimated risks, and an absence of phased execution planning. Political imperatives, rather than technical feasibility, appeared to influence project initiation and scale. The findings emphasize the importance of aligning project ambitions with verified resource availability, engaging sector-specific expertise early, and adopting phased, evidence-based implementation to safeguard cost efficiency, timely delivery, and scope adherence. Policy recommendations include mandatory feasibility studies, independent technical vetting, and governance reforms to insulate PPP projects from politically driven scope inflation.
- Chiswa, N. (2024) Unravelling Critical Success Factors in Public-Private Partnership Implementation. European Procurement & Public Private Partnership Law Review , 19, 39-60. https://doi.org/10.21552/epppl/2024/1/7
- Kaliba, C., Muya, M. and Mumba, K. (2009) Cost Escalation and Schedule Delays in Road Construction Projects in Zambia. International Journal of Project Management , 27, 522-531. https://doi.org/10.1016/j.ijproman.2008.07.003
- Turgay, S. and Aydin, A. (2023) Risk Mitigation for SMEs: A Step-by-Step Guide to Implementing an Effective Framework. Financial Engineering and Risk Management , 6, 71-80.
- Othoche, B. (2021) Barriers and Limits to Climate Change Management in Developing Countries: Case Study of Kenya, Eastern African Region. In: Handbook of Climate Change Management , Springer, 3613-3632. https://doi.org/10.1007/978-3-030-57281-5_274
- Mazurkiewicz, A. (2018) Barriers of Technological Innovation Development and Implementation Encountered by R&D Organisations. Journal of Machine Construction and Maintenance , 108, 127-138.
- El-Kholy, A.M. and Akal, A.Y. (2021) Assessing and Allocating the Financial Viability Risk Factors in Public-Private Partnership Wastewater Treatment Plant Projects. Engineering, Construction and Architectural Management , 28, 3014-3040. https://doi.org/10.1108/ecam-05-2020-0373
- GCR, N. (2004) Cost Analysis of Inadequate Interoperability in the US Capital Facilities Industry. National Institute of Standards and Technology (NIST).
- Leshore, L. and Minja, D. (2019) Factors Affecting Implementation of Vision 2030 Flagship Projects in Kenya: A Case of the Galana-Kulalu Irrigation Scheme. International Academic Journal of Law and Society , 1, 395-410.
- Munene, H.W. and Kinoti, K. (2020) Monitoring and Evaluation Approaches and Performance of Galana Kulalu Maize Irrigation Project, Kenya. International Academic Journal of Information Sciences and Project Management , 3, 293-311.
- Müller-Mahn, D., Mkutu, K. and Kioko, E. (2021) Megaprojects—Mega Failures? The Politics of Aspiration and the Transformation of Rural Kenya. The European Journal of Development Research , 33, 1069-1090. https://doi.org/10.1057/s41287-021-00397-x
- Macharia, K.K. (2017) Effect of External Public Debt on the Exchange Rate in Kenya. International Journal in Management & Social Science , 5, 250-262.
- Barnard, A. (2010) What Is Theory of Constraints (TOC). Goldratt Group , 44, 479-489.