Use and Performance of the Force Account Method in Road Construction Projects: Evidence from Nairobi City County
- 1 Department of Civil, Construction and Environmental Engineering, Jomo Kenyatta University of Agriculture and Technology, Nairobi, Kenya
- 2 Department of Civil, Construction and Environmental Engineering, Jomo Kenyatta University of Agriculture and Technology, Nairobi, Kenya
- 3 Department of Civil, Construction and Environmental Engineering, Jomo Kenyatta University of Agriculture and Technology, Nairobi, Kenya
Abstract
This study investigated the use and performance of the force account method (FAM) in road construction projects in Nairobi City County, Kenya. The problem motivating the research was the absence of empirical evidence on the extent of FAM adoption in Kenya’s urban road sector and its actual performance outcomes, despite its growing prominence in public works. A descriptive cross-sectional design was applied, using both primary data collected through semi-structured questionnaires and secondary data from the Ministry of Roads and Transport reports. The target population comprised project managers, engineers, and procurement staff, with a census approach ensuring full coverage. The findings revealed that FAM accounted for 20.63% of road projects compared to 55.56% implemented through open tender. Projects delivered through FAM were significantly more efficient, averaging KES 107.24 million and 18 months, compared to KES 797.98 million and 48 months for open tender. Respondents reported that FAM projects largely complied with technical and safety standards, but challenges persisted in the form of cost overruns (mean maximum KES 71.8 million), inadequate supervision (78.3%), and managerial inefficiencies. Notably, defect rates were lowest in FAM projects (mean = 2.616), demonstrating better quality consistency relative to other methods. The study shows that FAM delivers measurable cost and time savings but faces persistent oversight and quality challenges. Policy recommendations include enhancing supervisory capacity, strengthening financial accountability, and expanding training for technical staff. Future research should assess the long-term sustainability of FAM projects and explore cross-county comparisons to evaluate broader applicability in Kenya’s infrastructure sector.
- Mabunda, N. (2023) Road Infrastructure as a Driving Force towards Socio-Economic Development in the South African Rural Areas. IAHRW International Journal of Social Sciences Review , 11, 532-537.
- Lufiko, K.A. (2023) Influence of Force Account Approach on Performance of Construction Project in Public Sectors. Doctoral Dissertation, Institute of Accountancy Arusha (IAA).
- Daud, N. and Slawe, D. (2024) Evaluating the Impact of the Force Account Method on Value for Money in Public Construction Projects in Tanzania. NG Journal of Social Development , 14, 71-84. https://doi.org/10.4314/ngjsd.v14i2.4
- Farrell, F.B. (2022) A Cost Comparison Study of Force Account and Contract Construction on Five Secondary Projects in North Carolina. https://onlinepubs.trb.org/Onlinepubs/hrbproceedings/35/35-009.pdf
- Khakata, S. (2014) Procurement Methods and Operational Performance of State Corporations in Kenya. Doctoral Dissertation, University of Nairobi.
- Mugarula, S.C. (2023) Assessment of Effectiveness of Force Account on the Implementation of Construction Projects in Moshi District Council. Doctoral Dissertation, Moshi Co-Operative University (MoCU).
- Kibona, G., Kimario, H. and Kasambala, M. (2025) The Value of Professionalism: Implication for Value for Money in Projects Implemented by Force Account Procurement Method in Tanzania. African Journal of Accounting and Social Science Studie s , 6, 62-80. https://doi.org/10.64717/ajass.v6i2.203
- Matto, M.C. (2021) Identifying the Latent Shortcomings of Force Account Projects in Tanzania: The Case of Construction Projects in the Education Sector. Engineering , Construction and Architectural Management , 30, 787-804. https://doi.org/10.1108/ecam-06-2021-0525
- Mfugale, R. (2022) The Role of Force Account on the Construction and Rehabilitation of Projects in Public Secondary Schools at Iringa Rural District, Tanzania. International Journal of Research in Education Humanities and Commerce , 3, 256-256.
- Ombara, I. (2013) Transport Infrastructural Development in Kenya towards Enhanced Regional Integration: A Case of Eastern Africa Region. Doctoral Dissertation, University of Nairobi.
- Ngungati, G.E. (2024) The Effectiveness of Force Account Implementation on the Performance of Construction of Primary School. Doctoral Dissertation, IAA.
- Ameh, O.J. and Ogundare, O. (2013) Impact of Due Process Policy on Construction Projects Delivery in Nigeria. Journal of Building Performance , 4, 13-23.